Description: Ward
Manufacturing Cupola Project
Summary: This was a Turn Key Contract
to engineer and install a new hot blast
cupola and emission system. The following
is a list of equipment and systems that
were included in the project:
82"
liningless cupola
Upper stack and lid
Main blower with automatic air weight
control.
12 Million BTU after burner system with
proportional control
Upper stack water spray nozzle with proportional
water flow control
Dropout box including water sprays with
proportional water flow control
Hot blast recuperator
Flue Gas Cooler and Fan with proportional
control
TETS system for dust treatment of heavy
metals utilizing in stream injection
Eight module baghouse guaranteed to meet
MAC standards
Individual module offline cleaning
VFD
on Fan for proportional control
Broken Bag Detectors
Charge vibratory feeder
Charge bucket and skip hoist
Complete integrated PLC control system
with graphical operator interface and
Historical data logging