Description: Relocation
of B.M.D. Molding Machine, 250 ton per
hour sand preparation plant, cooling line
and pouring unit.
Contract: Complete system design
- construct contract with equipment specification
and procurement.
Schedule: 5 months to start-up.
Summary: Disassembly and shipment
of the foundry was completed in three
months. During demolition, foundations
were formed and poured at the new foundry
site in Anniston, Alabama. Equipment erection
and electrical installation was accomplished
in nine weeks; entitling EC&S to collect
the schedule performance bonus. Innovative
manpower scheduling and work shift organization
enables EC&S to successfully perform
to the most aggressive schedules.